Heller Electric has successfully completed numerous Design/Build projects, many of which we have been selected to work with the Owner, Architect and Engineer from the planning process to be able to deliver the best combination of top quality, high tech, efficient and economical electrical and low voltage solutions. Below is a listing of some of the Design/Build projects Heller Electric has successful completed.




Design-Build Projects Completed

 

Rose Hardy Middle School – 1819 35th Street, NW

80,000 sqft historic renovation

On-Time Completion: 6 months (Aug. 2008)

Contract: $1,956,000.00

WIP: Not required

CBE: Not Applicable

 

Bowen Metro Police –101 M Street, SW

110,000 sqft renovation

On-Time Completion: 7 months (May 2009)

Contract: $2,557,000.00

LEED – Silver Project

WIP: Not required

CBE: 100% participation met (Certified JV was established)


Petworth Library – 4200 Kansas Avenue, NW

22,000 sqft historic renovation

On-Time Completion: 12 months (Jan. 2012)

Contract: $1,140,000.00

LEED – Silver Project

WIP: Not required (76% of Apprentice hours by DC Residents)

CBE: 100% participation met (Certified JV was established)

 

Drew Elementary Phase 1 – 5600 Eads Street, NE

25,000 sqft PHASE 1 Renovation

On-Time Completion: 3 months (Aug. 2011)

Contract: $901,000.00

WIP: Not applicable

CBE: 100% participation met (Certified JV was established)

 

Janney Elementary School Modernization and Addition – 4130 Albemarle Street, NW

40,000 sqft Renovation and 60,000 sqft addition

On-Time Completion: 12 months (Aug. 2011)

Contract: $2,096,000.00

LEED – Gold Project

WIP: Goals exceeded – 61% of Apprentice hours worked by DC Residents, 16% Journeyman

CBE: 100% participation met (Certified JV was established)


Woodrow Wilson Sr. High School – 3950 Chesapeake Street, NW

411,000 sqft Historic Renovation

On-Time Completion: 10 months (Aug. 2011)

Contract: $11,820,000.00

LEED – Gold Project

WIP: Goals exceeded – 74% of Apprentice hours worked by DC Residents, 12% Journeyman

CBE: 51% participation met


Ketcham Elementary Phase 1 – 1919 15th Street, NE

25,000 sqft PHASE 1 Renovation

On-Time Completion: 3 months (Aug. 2012)

Contract:  $1,771,000.00

WIP: Goals exceeded – 99% of Apprentice hours worked by DC Residents, 40% Journeyman

CBE: 50% participation met


Brookland at Bunker Hill Elementary Phase 1 – 1401 Michigan Avenue, NE

25,000 sqft PHASE 1 Renovation

On-Time Completion: 3 months (Aug. 2012)

Contract: $1,160,000.00

WIP: Goals exceeded – 75% of Apprentice hours worked by DC Residents, 31% Journeyman

CBE: 35% participation met


Cardozo High School – 1200 Clifton Street, NW

430,000 sqft historic renovation

On-Time Completion: 18 Months (Aug. 2013)

LEED – Gold Project

WIP: Goals exceeded – 100% of Apprentice hours by DC Residents, 36% Journeyman

CBE: 52% participation

 

Ft. Stanton Recreation Center – 1812 Erie Street, SE

60,000 sqft New Construction

On-Time Completion: 12 Months (Mar. 2013)

LEED – Silver Project

WIP: N/A

CBE: 100% participation met (CBE JV established)

 

Raymond Recreation Center – 915-A Spring Road, NW

60,000 sqft New Construction

On-Time Completion: 12 Months (Dec. 2012)

LEED – Silver Project

WIP: Goals exceeded – 48% of Apprentice hours worked by DC Residents

CBE: 40% participation

 

GMU North East Sector Development – Fairfax, VA

510,000 sqft new construction including: 4 new dorms, dining, and fitness facilities

On-Time Completion: 24 Months (July 2009)

Contract: $11,221,000.00

WIP: N/A

CBE: N/A

 

GMU Housing 7C – Fairfax, VA

220,000 sqft new construction including: 2 new dorms facilities

On-Time Completion: 16 Months (Dec. 2011)

Contract: $5,496,000.00

WIP: N/A

CBE: N/A


Roosevelt High School Modernization – 4301 13th St, NW

340,000 sqft renovation including: Main Power, Lighting, Theater, and Site

On-Time Completion: 5 Months (Oct. 2015)

Contract: $5,565,000.00

WIP: 54%

CBE: N/A

 

Ballou High School – 3401 4th Street, SE

390,000 sqft new construction including

Power, Lighting, AV, Fire Alarm

On-Time Completion: 24 Months (Dec. 2015)

Contract: $17,940,000

WIP: 46%

CBE: 50%

 

Ballou Phase 2 Sports Field –  3401 4th Street, SE

New Sports Field including:

Power, Lighting, MUSCO Lighting, AV

On-Time Completion: 2.5 Months per phase (September 2016)

Contract: $4,711,000

WIP: 41%

CBE: 48%

 

Payne Elementary Phase 1&2–  1445 C Steet, SE

80,000 sqft renovation including:

Power, Lighting, AV, Fire Alarm, Security

On-Time Completion: 2.5 Months per phase (August 2015)

Contract: $4,711,000

WIP: 36%

CBE: 50%